Multiple Choice Questions (MCQs) for Class 10 Mathematics: Time and Work
Access targeted multiple-choice questions for Time and Work designed to align with the latest CBSE academic syllabus for Class 10 Mathematics. These objective practice sets help students evaluate their conceptual understanding and improve exam readiness.
Practice Time and Work MCQs for Class 10 Mathematics
Navigate directly to the 50 objective questions for Time and Work using the digital viewer below. Each practice set includes verified answer keys, allowing students to instantly cross-check their work and identify areas requiring further revision.
Multiple Choice Questions
(a) 16 hrs 40 minutes
(b) 18 hrs 40 minutes
(c) 20 hrs
(d) 17 hrs 30 minutes
Show Answer & Explanation
Answer: (a) 16 hrs 40 minutes
Explanation:
1. Because 10% of the water leaks away, only 90% of the water stays
2. Time = 15/0.9 = 16 2/3 hrs = 16 hrs 40 minutes.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 50 minutes
(b) 40 minutes
(c) 80 minutes
(d) 100 minutes
Show Answer & Explanation
Answer: (b) 40 minutes
Explanation:
1. Meena types 50 words/min and Leena types 40 words/min, so together 90 words/min
2. Time = 3600/90 = 40 minutes.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) Rs. 115
(b) Rs. 92
(c) Rs. 200
(d) Rs. 250
Show Answer & Explanation
Answer: (b) Rs. 92
Explanation:
1. C's part = 1 − 19/23 = 4/23
2. C's payment = 4/23 × 529 = Rs. 92.
Teacher's Note:
1. Payment is proportional to the work done.
(a) 16
(b) 15
(c) 20
(d) None of the above
Show Answer & Explanation
Answer: (c) 20
Explanation:
1. One man does 1/240 per day and one child does 1/480 per day
2. 8 men + 8 children: 8/240 + 8/480 = 1/30 + 1/60 = 1/20
3. They take 20 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 6 days
(b) 7 days
(c) 8 days
(d) 9 days
Show Answer & Explanation
Answer: (a) 6 days
Explanation:
1. Ram does 8/12 = 2/3 of the work
2. Remaining 1/3 is done by Rajan in 18/3 = 6 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 24 days
(b) 18 days
(c) 12 days
(d) 9 days
Show Answer & Explanation
Answer: (c) 12 days
Explanation:
1. B takes 18 days
2. Together: 1/36 + 1/18 = 1/12 per day, so 12 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 36 men
(b) 24 men
(c) 21 men
(d) None of these
Show Answer & Explanation
Answer: (b) 24 men
Explanation:
1. 24 men made half the road in 48 days, so the remaining half in 24 days needs 24 × 48/24 = 48 men
2. Extra men = 48 − 24 = 24.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 15
(b) 14
(c) 12
(d) 11
Show Answer & Explanation
Answer: (c) 12
Explanation:
1. Total work = 20 × 9 × 12 = 2160 man-hours
2. N × 12 × 15 = 2160, so N = 12 men.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 4 days
(b) 6 days
(c) 8 days
(d) 12 days
Show Answer & Explanation
Answer: (c) 8 days
Explanation:
1. C = 1/6 − 1/8 = 1/24 and A = 1/6 − 1/12 = 1/12
2. A + C = 1/12 + 1/24 = 1/8, so 8 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 1/4
(b) 1/10
(c) 7/15
(d) 8/15
Show Answer & Explanation
Answer: (d) 8/15
Explanation:
1. Work in one day = 1/15 + 1/20 = 7/60
2. In 4 days = 28/60 = 7/15
3. Left = 8/15.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 7 min
(b) 8 min
(c) 9 min
(d) 10 min
Show Answer & Explanation
Answer: (b) 8 min
Explanation:
1. A works 18 minutes: 18/24 = 3/4
2. B must fill the remaining 1/4: t/32 = 1/4, so t = 8 min.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 10
(b) 5
(c) 15
(d) 20
Show Answer & Explanation
Answer: (b) 5
Explanation:
1. Together in 4 days: 4 × (1/10 + 1/15) = 4 × 1/6 = 2/3
2. Remaining 1/3 takes B 15/3 = 5 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 36
(b) 18
(c) 48
(d) 30
Show Answer & Explanation
Answer: (a) 36
Explanation:
1. A + B = 1/24 with A = 2B gives 3B = 1/24, so B = 1/72 and A = 1/36
2. A alone takes 36 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 30
(b) 25
(c) 24
(d) 20
Show Answer & Explanation
Answer: (c) 24
Explanation:
1. Together in one day: 1/16 + 1/20 + 1/30 = 35/240 = 7/48
2. One work takes 48/7 days, so 3.5 works take 3.5 × 48/7 = 24 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 50
(b) 25
(c) 30
(d) 45
Show Answer & Explanation
Answer: (a) 50
Explanation:
1. Nitu does the whole work in 25 days, so in 6 days she does 6/25
2. Remaining 19/25 takes Deepak 38 days, so the whole takes 38 × 25/19 = 50 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 10
(b) 9
(c) 8
(d) 6
Show Answer & Explanation
Answer: (c) 8
Explanation:
1. N × 12 × 5 = (N/2) × 15 × h
2. 60 = 7.5h, so h = 8 hours a day.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 40, 80, 100
(b) 60, 120, 120
(c) 50, 100, 120
(d) 60, 100, 80
Show Answer & Explanation
Answer: (b) 60, 120, 120
Explanation:
1. A = 2B and A + C = 3B give C = B
2. A + B + C = 4B = 1/30, so B = C = 1/120 and A = 1/60
3. A takes 60 days, B and C take 120 days each.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) P
(b) Q
(c) R
(d) Cannot be determined
Show Answer & Explanation
Answer: (a) P
Explanation:
1. Total work: 5p + 10q + 15r = 1 with q = 1/30, so 5p + 15r = 2/3
2. Q's part = 10/30 = 1/3
3. R's part = 15r < 15/45 = 1/3 and P's part = 5p = 2/3 − 15r > 1/3
4. P completed the maximum part.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
(a) 24
(b) 6
(c) 4
(d) 26
Show Answer & Explanation
Answer: (b) 6
Explanation:
1. After d days the food left = 1500(30 − d) man-days
2. It feeds 1800 men for 26 − d days: 1500(30 − d) = 1800(26 − d)
3. 45000 − 1500d = 46800 − 1800d, so d = 6 days.
Teacher's Note:
1. Treat the whole work as 1; a person finishing in n days does 1/n of the work per day.
2. Add the daily work of people working together and take the reciprocal for the time.
Free study material for Mathematics
Time and Work Objective Questions & Solutions for Class 10 Mathematics
Class 10 Mathematics Time and Work Objective Test Questions
Explore reliable practice questions for Time and Work tailored for Class 10 Mathematics learners. Use these multiple-choice formats to evaluate preparedness and strengthen problem-solving skills.
NCERT-Aligned Objective Questions and Solutions
Cross-reference your completed choices with comprehensive NCERT solutions for Class 10 Mathematics to ensure absolute clarity across all sub-topics in this chapter.
Next Steps in Your Exam Preparation
Explore our broader library of printable assignments, chapter notes, and mock tests designed to support continuous revision and secure higher marks in CBSE assessments.
FAQs
You can get most exhaustive CBSE Class 10 Mathematics Time and Work MCQs Set 19 for free on StudiesToday.com. These MCQs for Class 10 Mathematics are updated for the 2026-27 academic session as per CBSE examination standards.
Yes, our CBSE Class 10 Mathematics Time and Work MCQs Set 19 include the latest type of questions, such as Assertion-Reasoning and Case-based MCQs. 50% of the CBSE paper is now competency-based.
By solving our CBSE Class 10 Mathematics Time and Work MCQs Set 19, Class 10 students can improve their accuracy and speed which is important as objective questions provide a chance to secure 100% marks in the Mathematics.
Yes, Mathematics MCQs for Class 10 have answer key and brief explanations to help students understand logic behind the correct option as its important for 2026 competency-focused CBSE exams.
Yes, you can also access online interactive tests for CBSE Class 10 Mathematics Time and Work MCQs Set 19 on StudiesToday.com as they provide instant answers and score to help you track your progress in Mathematics.