Here is Prefabricated Structures MCQ Questions and Answers in Civil Engineering for your studies. Download chapter-wise Civil Engineering MCQs with answers in PDF format. Built for current exams, practicing Prefabricated Structures questions builds strong skills and boosts your test scores.
Practice Civil Engineering Prefabricated Structures MCQs
For Civil Engineering exams, practicing questions for Prefabricated Structures is very useful. Use these multiple-choice questions with answers to check how much you know and fix your mistakes.
Prefabricated Structures Questions and Answers for Civil Engineering
Question. Depending on the degree of workability and placing condition determine the
(a) slump value
(b) the maximum size of aggregate
(c) the amount of mixing water
(d) the minimum water-cement ratio
Answer : A
Question. Which is the system for prefabrication?
(a) closed pfs.
(b) open pfs
(c) floor pfs
(d) roof system
Answer : B
Question. Which are the characteristics of Materials used for construction of PFS?
(a) thermal insulation property
(b) combustibility
(c) heavier materials
(d) none of the above
Answer : A
Question. What demands for disuniting the prefabricated structures?
(a) less weight
(b) quality
(c) transportation and placing of structures
(d) design constraints
Answer : C
Question. At what point in the members disuniting should be done?
(a) at minimum shear points
(b) at corners or points of minimum moments
(c) at points of maximum moment
(d) at intersections
Answer : B
Question. During disuniting joints are provided at
(a) at corners or point of minimum bending moment joint
(b) at center of member
(c) at intersections
(d) at tension joints
Answer : A
Question. The elastic rebound theory is an explanationfor how ... is spread duringearthquakes
(a) load
(b) stress
(c) energy
(d) intensity of load
Answer : C
Question. Choose the correct answer in terms of special requirements for building in High Seismic Zones
(a) the height of the building shall generally restricted to 5 stores in zone iv
(b) the height of the building shall generally restricted to 7 stores in zone iv
(c) the height of the building shall generally restricted to 8 stores in zone iv
(d) the height of the building shall generally restricted to 10 stores in zone iv
Answer : D
Question. Which of the following does not comes under the types of progressive collapse
(a) domino-type collapse
(b) section type collapse
(c) stability type collapse
(d) mixed-type collapse
Answer : C
Question. Which of the following stress affects the Demoulding?
(a) stripping stress
(b) dynamic stress
(c) erection stress
(d) lifting stress
Answer : A
Question. What are the Advantages of standardization?
(a) easier for design
(b) easier to manufacture
(c) easier to erection and completion
(d) all of the above
Answer : D
Question. Slip form construction is a construction method in which concrete is poured into
(a) static firm
(b) continuously moving firm
(c) vertically moving firm
(d) interrupted firms
Answer : D
Question. If Joint deformation in the prefabricated structures is allowed It means
(a) allowance for joint flexibility
(b) allowance for stress
(c) allowance for swaying
(d) allowance for stress accumulation
Answer : A
Question. During design of elements in prefabricated structures due consideration should be given to
(a) quality materials
(b) stresses developed during handling the members
(c) minimum factor of safety
(d) all of these
Answer : D
Question. Damping is the energy dissipation properties of a material or system under stress.
(a) dynamic stress
(b) static stress
(c) non cyclic stress
(d) cyclic stress
Answer : D
Question. Choose the correct answer in terms of special requirements for building in High Seismic Zones
(a) the height of the building shall generally restricted to 5 stores in zone v
(b) the height of the building shall generally restricted to 6 stores in zone v
(c) the height of the building shall generally restricted to 7 stores in zone v
(d) the height of the building shall generally restricted to 8 stores in zone v
Answer : A
Question. Which of the following stress affects the Transportation?
(a) stripping stress
(b) dynamic stress
(c) erection stress
(d) lifting stress
Answer : B
Question. Which of the below equipment is not used for hoisting of prefabricated components?
(a) stationary cranes
(b) cranes on rails
(c) mobile cranes
(d) all of the above
Answer : D
Question. The large reinforced concrete roofing members in prefabricated structures are
(a) directly supported by main girders
(b) directly supported on panel members
(c) two way reinforcement is provided
(d) provided with less reinforcement
Answer : A
Question. In places where transportation of large members is difficult what kind of fabrication is preferred?
(a) plant prefabrication
(b) site fabrication
(c) standardisation
(d) prefabricate systems
Answer : B
Question. Which of the following defines Magnitude?
(a) the severity of earthquake shaking is assessed using a descriptive scale
(b) quantitative measure of the size of the earthquake at its source
(c) both a &b
(d) none of the above
Answer : B
Question. How may methods are available for Manufacture of precast concrete elements?
(a) one
(b) two
(c) three
(d) four
Answer : B
Question. Prefabrication is a ................... construction method
(a) automotive
(b) modern
(c) established
(d) industrialised
Answer : D
Question. Why should we give allowance for joint deformation?
(a) to take care of the joints
(b) to take care of the deformation due toir regularities
(c) to take care of the disuniting of member
(d) to take care of moments in the members
Answer : B
Question. Plant fabrication is suited better for
(a) large number of small prefabricates
(b) large e long panel members
(c) standard is members
(d) limited production
Answer : A
Question. In a Prefabricated R C floors in a cyclone prone zone the Structural deck concrete of grade not leaner than .............. should be provided over pre-cast components to act monolithic with them.
(a) m10
(b) m15
(c) m20
(d) m25
Answer : C
Question. Which one is not the characteristic of Materials used for construction of PFS?
(a) non durability
(b) non combustibility
(c) lighter materials
(d) none of the above
Answer : A
Question. Certain geometric discipline using practical approaches which relate to setup coordination and measurement of components and spaces in building design is introduced in
(a) standardization
(b) modular coordination
(c) remoulding
(d) moulding
Answer : B
Question. What is the disadvantages of disuniting of structures?
(a) easy to transport the members from casting yard to site.
(b) requires lesser capacity of lifting arrangements.
(c) identifying the joint location
(d) require less amount of supporting arrangements
Answer : C
Question. Transportation of precast members accounts for about
(a) 20-25%ofthecostof production and assembling
(b) 10-15% of the cost of production and assembling
(c) 10-20% of the cost of production and assembling
(d) 5-15% of the cost of production and assembling
Answer : B
Question. How many methods are generally used to avoid the disproportionate collapse in a building?
(a) oone
(b) two
(c) three
(d) zero
Answer : C
Question. What is the nature erection stresses?
(a) dynamic
(b) static
(c) compatible
(d) rigid
Answer : A
Question. What is disuniting of Structure?
(a) dividing into panels
(b) organizing the panels
(c) erecting the panels
(d) making into smaller members
Answer : D
Question. The economy of cross section is measured by
(a) shape factor
(b) form factor
(c) section modulus
(d) material
Answer : B
Question. Choose the correct answer.
(a) converting static load into dynamic load is known as equivalent design loads.
(b) converting dynamic load into static load is known as equivalent design loads.
(c) both a &b
(d) none of the above
Answer : B
Question. Which method is not adopted in precasting?
(a) tilting mould method
(b) long line method
(c) extrusion method
(d) static method
Answer : D
Question. Based on load transfer the joints can be classified as
(a) tension joint
(b) compression joint
(c) flexural joint
(d) all of these
Answer : D
Question. .................... is the factor used to obtain the design seismic force depending on the functional use of the structure, characterized by hazardous consequences of its failure, its post-earthquake functional need, historic value, or economic importance.
(a) importance factor
(b) response reduction factor
(c) all of the above
(d) none of the above
Answer : A
Question. In the production of prefabricated structures how does the material used in construction affect the element?
(a) material quality and economic design
(b) smaller members
(c) disuninting of members
(d) joints
Answer : A
Free study material for Civil Engineering
Verified Prefabricated Structures MCQs with Solutions (Civil Engineering)
Evaluate your progress using these targeted Prefabricated Structures MCQs built for Civil Engineering students. Download complete sets of Civil Engineering MCQs in PDF for seamless daily revision.
Expert-Curated Prefabricated Structures Questions (Civil Engineering)
Gain a competitive edge in Civil Engineering with carefully validated questions and answers. Complement your learning by exploring our full range of Civil Engineering study material.
Verified Prefabricated Structures Solutions (Civil Engineering)
Tackle complex concepts using step-by-step solutions attached to each Civil Engineering MCQ designed specifically for Prefabricated Structures practice.
Maximize Accuracy in Civil Engineering Prefabricated Structures
Turn concepts into permanent knowledge with routine drills for Prefabricated Structures. Validate your current speed by taking our dedicated online Civil Engineering MCQ test.
Evaluate Readiness for Civil Engineering Exams
Ensure total preparedness by cross-checking your core concepts in Prefabricated Structures against our extensive collection of Civil Engineering sample papers.
FAQs
You can download the MCQs for Civil Engineering Prefabricated Structures for latest session from StudiesToday.com
Yes, the MCQs issued for Civil Engineering Prefabricated Structures have been made available here for latest academic session
Learning Prefabricated Structures based MCQs will help students improve their overall understanding of important concepts and topics and help to score well in Civil Engineering exams.
You can practice Prefabricated Structures through worksheets, textbooks and online quizzes provided by studiestoday.com.
You can find Civil Engineering Prefabricated Structures MCQs on educational websites like studiestoday.com, online tutoring platforms, and in sample question papers provided on this website.
To prepare for Prefabricated Structures MCQs, refer to the concepts links provided by our teachers and download sample papers for free.
Yes, there are many online resources that we have provided on studiestoday.com available such as practice worksheets, question papers, and online tests for learning MCQs for Civil Engineering Prefabricated Structures
Yes, you can find printable Prefabricated Structures worksheets for Civil Engineering on studiestoday.com.
We have provided full database of free multiple choice questions with answers on studiestoday.com for Civil Engineering Prefabricated Structures